| Reference | EN 61850-5:2013 |
|---|---|
| Title | Communication networks and systems for power utility automation - Part 5: Communication requirements for functions and device models |
| Project Number | 23426 |
| Abstract/Scope | IEC 61850-5:2013 applies to power utility automation systems with the core part of substation automation systems (SAS); it standardizes the communication between intelligent electronic devices (IEDs) and defines the related system requirements to be supported. The major technical changes with regard to the previous edition are as follows: - extension from substation automation systems to utility automation systems; - inclusion of interfaces for communication between substations; - requirements from communication beyond the boundary of the substation. |
| Status |
Published
|
Status
| Current Stage code | 6060 |
|---|---|
| Current Stage code date | 2013-05-03 |
| Current Stage code deadline | 2013-12-06 |
| Deadline date for vote |
Legal
| Directive(s) | |
|---|---|
| Mandate(s) | |
| Order Voucher |
Details
| IEC Technical Body | IEC/TC 57 |
|---|---|
| Reference Document | IEC 61850-5:2013 (EQV) |
| ICS | 33.200 - Telecontrol. Telemetering |
| Keywords | Communication; Network; Substation; Function; Device model |
| Note | Supersedes EN 61850-5:2003 |
| A-Deviation(s) | |
| Special National Condition(s) |
Environment
|
Clause
|
Categories - Aspects
|
Product Life Cycle
|
Information
|
|---|
History
Implementation Dates
| date of Ratification (DOR) (1) | 2013-03-06 |
|---|---|
| date of Availability (DAV) (2) | 2013-05-03 |
| date of Announcement (DOA) (3) | 2013-06-06 |
| date of Publication (DOP) (4) | 2013-12-06 |
| date of Withdrawal (DOW) (5) | 2016-03-06 |
Relations
| Supersedes | EN 61850-5:2003 |
|---|---|
| Superseded by | |
| Normative reference (6) |
EN 61000-4-15:2011
IEC/TS 61850-2:2003 EN 61850-6:2010 EN 81346-1:2009 Cigre JWG 34./35.11:2007 |
(1) Date of ratification (dor) date when the Technical Board notes the approval of an EN (and HD for CENELEC), from which time the standard may be said to be approved
(2) Date of availability (dav) date when the definitive text in the official language versions of an approved CEN/CENELEC publication is distributed by the Central Secretariat
(3) Date of announcement (doa) latest date by which the existence of an EN (and HD for CENELEC), a TS or a CWA has to be announced at national level
(4) Date of publication (dop) latest date by which an EN has to be implemented at national level by publication of an identical national standard or by endorsement
(5) Date of withdrawal (dow) latest date by which national standards conflicting with an EN (and HD for CENELEC) have to be withdrawn
(6) This list of normative references is purely indicative. The only official list of normative reference is the list of the published standard.