CENELEC

Project
| Reference | EN 60076-10:2001 |
|---|---|
| Title | Power transformers - Part 10: Determination of sound levels |
| Project Number | 13164 |
| Abstract/Scope | Defines sound pressure and sound intensity measurement methods by which sound power levels of transformers, reactors and their associated cooling auxiliaries may be determined. The methods are applicable to transformers and reactors covered by the EN 60076 series, EN 60289, EN 60726 and the EN 61378 series, without limitation as regards size or voltage and when fitted with their normal cooling auxiliaries. This standard is primarily intended to apply to measurements made at the factory. Conditions on-site may be very different because of the proximity of objects, including other transformers. Nevertheless, the same general rules as are given in this standard may be followed when on-site measurements are made. |
| Status |
Published
|
Status
| Current Stage code | 6060 |
|---|---|
| Current Stage code date | 2001-07-10 |
| Current Stage code deadline | 2002-03-01 |
| Deadline date for vote |
Legal
| Directive(s) | |
|---|---|
| Mandate(s) | |
| Order Voucher |
Details
| IEC Technical Body | IEC/TC 14 |
|---|---|
| Reference Document | IEC 60076-10:2001 (EQV) |
| ICS | 29.180 - Transformers. Reactors |
| Keywords | Transformer; Power transformer; Sound level |
| Note | EN following parallel vote * Supersedes EN 60551:1992 + A1:1997 |
| A-Deviation(s) | |
| Special National Condition(s) |
Environment
History
Implementation Dates
| date of Ratification (DOR) (1) | 2001-06-01 |
|---|---|
| date of Availability (DAV) (2) | 2001-07-10 |
| date of Announcement (DOA) (3) | 2001-09-01 |
| date of Publication (DOP) (4) | 2002-03-01 |
| date of Withdrawal (DOW) (5) | 2004-06-01 |
Relations
| Supersedes | EN 60551:1992 EN 60551:1992/A1:1997 |
|---|---|
| Superseded by | |
| Normative reference (6) | ISO 3746:1995 ISO 9614-1:1993 EN 60076-3:2001 EN 60289:1994 A11:2002 EN 60651:1994 EN 60726:2003 EN 61043:1994 EN 61378-1:1998 corr. November 1998 |
(1) Date of ratification (dor) date when the Technical Board notes the approval of an EN (and HD for CENELEC), from which time the standard may be said to be approved
(2) Date of availability (dav) date when the definitive text in the official language versions of an approved CEN/CENELEC publication is distributed by the Central Secretariat
(3) Date of announcement (doa) latest date by which the existence of an EN (and HD for CENELEC), a TS or a CWA has to be announced at national level
(4) Date of publication (dop) latest date by which an EN has to be implemented at national level by publication of an identical national standard or by endorsement
(5) Date of withdrawal (dow) latest date by which national standards conflicting with an EN (and HD for CENELEC) have to be withdrawn
(6) This list of normative references is purely indicative. The only official list of normative reference is the list of the published standard.