| Reference | EN 62271-209:2007 |
|---|---|
| Title | High-voltage switchgear and controlgear - Part 209: Cable connections for gas-insulated metal-enclosed switchgear for rated voltages above 52 kV - Fluid-filled and extruded insulation cables - Fluid-filled and dry-type cable-terminations |
| Project Number | 20608 |
| Abstract/Scope | This standard covers the connection assembly of fluid-filled and extruded cables to gas-insulated metal enclosed switchgear (GIS), in single- or three-phase arrangements where the cable-terminations are fluid-filled or dry type and there is a separating insulating barrier between the cable insulation and the gas insulation of the switchgear. |
| Status |
Published
|
Status
| Current Stage code | 6060 |
|---|---|
| Current Stage code date | 2007-11-21 |
| Current Stage code deadline | 2008-07-01 |
| Deadline date for vote |
Legal
| Directive(s) | |
|---|---|
| Mandate(s) | |
| Order Voucher |
Details
| IEC Technical Body | IEC/SC 17C |
|---|---|
| Reference Document | IEC 62271-209:2007 (EQV) |
| ICS | 29.130.10 - High voltage switchgear and controlgear |
| Keywords | Switchgear; Cable connection; Gas-insulated; Insulation; Fluid-filled cable |
| Note | IT A-deviation |
| A-Deviation(s) | IT |
| Special National Condition(s) |
Environment
|
Clause
|
Categories - Aspects
|
Product Life Cycle
|
Information
|
|---|
History
Implementation Dates
| date of Ratification (DOR) (1) | 2007-10-01 |
|---|---|
| date of Availability (DAV) (2) | 2007-11-21 |
| date of Announcement (DOA) (3) | 2008-01-01 |
| date of Publication (DOP) (4) | 2008-07-01 |
| date of Withdrawal (DOW) (5) | 2010-10-01 |
Relations
| Supersedes | |
|---|---|
| Superseded by | |
| Normative reference (6) | CIGRE Brochure 89, WG 21.06:1995 CIGRE WG 23-10 Report, ELECTRA 151:1993 HD 472 S1:1989 corr. February 2002 corr. prA1: prA2: A1:1995 IEC 60141-1:1993 IEC 60141-2:1963 EN 60694:1996 corr. April 1998 corr. May 1999 IEC 60840:2004 IEC 62067:2001 EN 62271-203:2004 |
(1) Date of ratification (dor) date when the Technical Board notes the approval of an EN (and HD for CENELEC), from which time the standard may be said to be approved
(2) Date of availability (dav) date when the definitive text in the official language versions of an approved CEN/CENELEC publication is distributed by the Central Secretariat
(3) Date of announcement (doa) latest date by which the existence of an EN (and HD for CENELEC), a TS or a CWA has to be announced at national level
(4) Date of publication (dop) latest date by which an EN has to be implemented at national level by publication of an identical national standard or by endorsement
(5) Date of withdrawal (dow) latest date by which national standards conflicting with an EN (and HD for CENELEC) have to be withdrawn
(6) This list of normative references is purely indicative. The only official list of normative reference is the list of the published standard.