CENELEC

Project
| Reference | EN 50521:2008/A1:2012 |
|---|---|
| Title | Connectors for photovoltaic systems - Safety requirements and tests |
| Project Number | 23550 |
| Abstract/Scope | This European Standard applies to connectors of application Class A according to EN 61730-1 for use in photovoltaic systems with rated voltages up to 1 500 V DC and rated currents up to 125 A per contact. This standard applies to connectors without breaking capacity but might be engaged and disengaged under voltage. NOTE For connectors according to Class B and C of EN 61730 as well as for protection for Class II equipment intended for use between 0 V and 120 V d.c. in photovoltaic-systems this standard may be used as a guide. |
| Status |
Published
|
Status
| Current Stage code | 6060 |
|---|---|
| Current Stage code date | 2012-07-13 |
| Current Stage code deadline | 2013-06-25 |
| Deadline date for vote |
Legal
| Directive(s) | |
|---|---|
| Mandate(s) | |
| Order Voucher |
Details
| IEC Technical Body | |
|---|---|
| Reference Document | |
| ICS | 29.120.30 - Plugs, socket-outlets, couplers |
| Keywords | Connector; Photovoltaic; Safety |
| Note | 2012-05-23 - Publication editing allocated to svandriessche@cencenelec.eu |
| A-Deviation(s) | |
| Special National Condition(s) |
Environment
|
Clause
|
Categories - Aspects
|
Product Life Cycle
|
Information
|
|---|
History
Implementation Dates
| date of Ratification (DOR) (1) | 2012-06-25 |
|---|---|
| date of Availability (DAV) (2) | 2012-07-13 |
| date of Announcement (DOA) (3) | 2012-12-25 |
| date of Publication (DOP) (4) | 2013-06-25 |
| date of Withdrawal (DOW) (5) | 2015-06-25 |
Relations
| Supersedes | |
|---|---|
| Superseded by | |
| Normative reference (6) |
(1) Date of ratification (dor) date when the Technical Board notes the approval of an EN (and HD for CENELEC), from which time the standard may be said to be approved
(2) Date of availability (dav) date when the definitive text in the official language versions of an approved CEN/CENELEC publication is distributed by the Central Secretariat
(3) Date of announcement (doa) latest date by which the existence of an EN (and HD for CENELEC), a TS or a CWA has to be announced at national level
(4) Date of publication (dop) latest date by which an EN has to be implemented at national level by publication of an identical national standard or by endorsement
(5) Date of withdrawal (dow) latest date by which national standards conflicting with an EN (and HD for CENELEC) have to be withdrawn
(6) This list of normative references is purely indicative. The only official list of normative reference is the list of the published standard.