CENELEC

Project
| Reference | EN 60420:1993 |
|---|---|
| Title | High-voltage alternating current switch-fuse combinations |
| Project Number | 2999 |
| Abstract/Scope | This standard applies to three-pole units for public and industrial distribution systems which are functional assemblies of switches including switch-disconnectors and current-limiting fuses and thus able to interrupt: -any load current up to the rated breaking current of the switch; -any over-current up to the rated short-circuit breaking current of the combination by which automatic interruption is initiated. This standard applies to combinations designed with rated voltages above 1 kV and below 52 kV for use on three-phase alternating current systems of either 50 Hz or 60 Hz. |
| Status |
Withdrawn
|
Status
| Current Stage code | 6060 |
|---|---|
| Current Stage code date | 1993-08-30 |
| Current Stage code deadline | 1994-04-01 |
| Deadline date for vote |
Legal
| Directive(s) | |
|---|---|
| Mandate(s) | |
| Order Voucher |
Details
| IEC Technical Body | IEC/SC 17A |
|---|---|
| Reference Document | IEC 60420:1990 (EQV) |
| ICS | |
| Keywords | Switch; HV; Switch-fuse combination |
| Note | Superseded by EN 62271-105:2003 |
| A-Deviation(s) | |
| Special National Condition(s) |
Environment
|
Clause
|
Categories - Aspects
|
Product Life Cycle
|
Information
|
|---|
History
Implementation Dates
| date of Ratification (DOR) (1) | 1993-07-06 |
|---|---|
| date of Availability (DAV) (2) | 1993-08-30 |
| date of Announcement (DOA) (3) | 1993-10-01 |
| date of Publication (DOP) (4) | 1994-04-01 |
| date of Withdrawal (DOW) (5) | 1994-04-01 |
Relations
| Supersedes | |
|---|---|
| Superseded by | EN 62271-105:2003 |
| Normative reference (6) | IEC 60050-151:1978 IEC 60050-441:1984 HD 348 S7:1998 EN 60129:1994 IEC 60137:1984 HD 355.1 S3:1995 EN 60282-1:1993 corr. December 1997 HD 187 S4:1989 IEC 60466:1987 HD 448 S4:1996 IEC 60787:1983 |
(1) Date of ratification (dor) date when the Technical Board notes the approval of an EN (and HD for CENELEC), from which time the standard may be said to be approved
(2) Date of availability (dav) date when the definitive text in the official language versions of an approved CEN/CENELEC publication is distributed by the Central Secretariat
(3) Date of announcement (doa) latest date by which the existence of an EN (and HD for CENELEC), a TS or a CWA has to be announced at national level
(4) Date of publication (dop) latest date by which an EN has to be implemented at national level by publication of an identical national standard or by endorsement
(5) Date of withdrawal (dow) latest date by which national standards conflicting with an EN (and HD for CENELEC) have to be withdrawn
(6) This list of normative references is purely indicative. The only official list of normative reference is the list of the published standard.